In August 2014 MeyGen secured funding for construction of the Phase 1A project, from various external investors including Crown Estate Scotland, the then Department of Energy & Climate Change (now Department for Energy Security & Net Zero), Scottish Enterprise via the Renewable Energy Investment Fund (delivered by the Scottish Investment Bank) (“REIF”) and Highlands and Islands Enterprise (“HIE”).
Phase 1A of the MeyGen project consists of an array of three HS1000 Mk 1 tidal turbines from Andritz Hydro Hammerfest (“AHH”), each rated at 1.5MW, and one AR1500 tidal turbine from Atlantis, also rated at 1.5MW. The AHH turbines, along with each turbine’s share of the common infrastructure, are known as the AHH Project; whilst the Atlantis turbine along with its share of the common infrastructure is known as the Atlantis Project. Some Funders invested in both the AHH Project and the Atlantis Project, whilst others only invested in the AHH Project.
As part of the funding investment documentation there is a requirement for an ongoing technical advisor. This tender document is aimed at filling this position.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Baldock Energy | 11930016 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £92,190 initial term | 2 | Baldock Energy | complete |