Generally the works comprise installation of an internal support structure to the Great Hall and Marions Extension buildings at Kisimul Castle, Barra. The support stucture comprises timber beams and joists supported off masonry piers.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| JML Contracts Ltd | SC293557 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 60 days | £124,370 initial term | 3 | JML Contracts Ltd | complete |