The propose of this project is to restore an otherwise degraded area of peatland through the use of standard restoration techniques (that can be found within the Peatland Action Technical compendium (https://www.nature.scot/doc/peatland-action-technical-compendium . The project area is 91 ha that has been artificially drained. All details contained with the statement of requirement.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| NetZero(North) limited | 14448604 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Sept 2025 – Nov 2025 | £139,403 initial term | 3 | NetZero(North) limited | complete |
Government spending data: This supplier has received £323,603 in 16 payments (over £25k) from Forestry Commission (2026-04-23 to 2026-08-18). View full payment history →