Shetland Islands Council proposes to refurbish the existing Brae Community Centre. The building is timber framed with blockwork outer leaf. Gross external area = 506m².
Building refurbishment comprises the upgrading of the insulation fabric of building including floors, walls, ceilings, external doors. Internal reconfiguration of partitions in part of the building (200m²) including new toilets and kitchen.
Redecorate throughout, repaint walls, ceilings, doors, skirtings, new floor coverings.
Services upgrades, new heating, lighting, ICT installations. New solar panel installation.
Provision of car charging facilities and ebike charging and storage.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 150 days | - | active |