It is envisaged the successful main contractor and their supply chain will be responsible for the specialist fit out of the Theatre and Cinemas.
A Multi Disciplinary design team have been appointed with MICA Architects as the lead designers.
The exact procurement route is still to be determined. However, the contract is expected bto be a JCT Design & Build.
Key Procurement Dates - Subject to procurement route:-
Approval of re design Single Stage Tender 20 Oct 23 Two Stage Tender 20 Oct 23
Public Consultation Single Stage Tender Dec 23 Two Stage Tender Dec 23
RIBA 3 Completion Single Stage Tender 26 Jan 24 Two Stage Tender 26 Jan 24
Submit Planning Application Single Stage Tender 2 Feb 24 Two Stage Tender 2 Feb 24
Contractor Procurement Single Stage Tender 5 April 24 Two Stage Tender 15 Dec 24
1st Stage / SQ
Contractor Award Single Stage Tender 1 July 24 Two Stage Tender 12 Jan 24
RIBA 4 Completion Single Stage Tender 12 April 24 Two Stage Tender 12 April 24
Planning Determination Single Stage Tender 24 May 24 Two Stage Tender 24 May 24
Contractor Develops Single Stage Tender 21 June 24 Two Stage Tender 24 May 24
Fixed Price
Approval Single Stage Tender 28 June 24 Two Stage Tender 31 May 24
Issue of FBC Single Stage Tender 26 July 24 Two Stage Tender 28 June 24
Maltings Decant Single Stage Tender June -July 24 Two Stage Tender May-June 24
SOS Single Stage Tender 19 Aug 24 Two Stage Tender 22 July 24
Practical Completion Single Stage Tender 14 Aug 26 Two Stage Tender 17 July 26
Formal Opening Single Stage Tender 11 Dept 26 Two Stage Tender 14 Aug 26
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 | - | planned |