BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information.
Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Tilbury Douglas Construction Ltd | 00303359 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £2,000,000 initial term | 2 | Tilbury Douglas Construction Ltd | complete |
Government spending data: This supplier has received £1,318,276,059 in 3,734 payments (over £25k) from Department for Education, Department for Transport, Ministry of Defence, Leicestershire Partnership NHS Trust, HMCTS and 14 more public bodies (2012-06-13 to 2026-06-30). View full payment history →