The Client requires the provision of civil engineering roads maintenance and associated services.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Castleview Plant | - | - | 2 lots East Region (Tay) · Central Region | - |
| CR Contracting North LTD | SC404952 | - | 1 lot East Region (Moray and Aberdeenshire) | - |
| CR Contractors Tain Limited | SC606248 | - | 2 lots North Region (North) · East Region (Moray and Aberdeenshire) | - |
| G S Campbell (Contractors) Ltd | SC224407 | - | 2 lots West Region (North) · West Region (Central) | - |
| GTR Contracts Ltd | SC310883 | - | 2 lots South Region (Arran) · South Region (Mainland West) | - |
| MAM Contracting Ltd | SC273835 | - | 1 lot South Region (Mainland East) | - |
| McFadyens Contractors (Campbeltown) Ltd | SC059723 | - | 1 lot West Region (South) | - |
This procurement was divided into 12 lots, each awarded separately. 52 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 North Region (West) 1,080 days (≈3 yrs) | - | - | - | active |
| Lot 2 North Region (South) 1,080 days (≈3 yrs) | - | 7 | - | complete |
| Lot 3 North Region (North) 1,080 days (≈3 yrs) | £5,745,000 initial term | 5 | CR Contractors Tain Limited | complete |
| Lot 5 East Region (Moray and Aberdeenshire) 1,440 days (≈3.9 yrs) | £6,064,000 initial term | 2 | CR Contractors Tain Limited CR Contracting North LTD | complete |
| Lot 6 West Region (North) 1,080 days (≈3 yrs) | £3,846,000 initial term | 6 | G S Campbell (Contractors) Ltd | complete |
| Lot 7 West Region (Central) 1,080 days (≈3 yrs) | £6,119,000 initial term | 4 | G S Campbell (Contractors) Ltd | complete |
| Lot 8 West Region (South) 1,080 days (≈3 yrs) | £7,517,000 initial term | 3 | McFadyens Contractors (Campbeltown) Ltd | complete |
| Lot 9 Central Region 1,080 days (≈3 yrs) | £15,873,000 initial term | 5 | Castleview Plant | complete |
| Lot 10 South Region (Arran) 1,080 days (≈3 yrs) | £2,156,000 initial term | 2 | GTR Contracts Ltd | complete |
| Lot 11 South Region (Mainland West) 1,080 days (≈3 yrs) | £3,429,000 initial term | 6 | GTR Contracts Ltd | complete |
| Lot 12 South Region (Mainland East) 1,080 days (≈3 yrs) | £4,471,000 initial term | 6 | MAM Contracting Ltd | complete |
| Lot 4 East Region (Tay) 1,080 days (≈3 yrs) | £3,032,000 initial term | 6 | Castleview Plant | complete |
Weightings from the notice, applied to every lot.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.