The works comprise of play equipment & hard and soft landscaping for the creation of a new play area. This is based in the main park in Auchterarder, not from the A9, with an anticipated budget range of 300-350k GBP; anticipated start late September 2022, and anticipated practical completion by December with grass establishment in early 2023 depending on weather conditions.
| Supplier | Identifier | Award Value | Cross-References |
|---|---|---|---|
| Caley Construction Ltd | SC199849 | £265,108 | - |