Rehabilitation of H06/24 runway at Sumburgh Airport. Resurfacing works are also required at Apron Alpha and other minor assets across the airport.
Drainage and AGL works required.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Lagan Aviation & Infrastructure | NI627818 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £2,998,910 initial term | 3 | Lagan Aviation & Infrastructure | complete |
Government spending data: This supplier has received £37,560,074 in 21 payments (over £25k) from Ministry of Defence (2021-07-13 to 2025-05-27). View full payment history →