BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The project is being undertaken to protect the coastline to the north and east of the 18-36 runway, the primary runway at the airport. In recent decades the beach and dunes to the north and east of the airport have been subject to erosion. The extent of erosion is now such that if corrective action is not taken, it will soon impact on the existing infrastructure and potential operation of the airport.
The works include the procurement and installation of rock armour and reno mattress along the coastal boundary line of the airport, at the interface between the dunes and beach, including the return to the estuary.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Breedon Hebrides | - | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Oct 2021 – Nov 2022 | - | 2 | Breedon Hebrides | complete |
Weightings from the notice.
Changes the buyer published to this notice after it first appeared.
Allowance for resource issues due to summer annual leave
Indicative project cash-flow
NOTICE TO ALL TENDERERS
As part of your submission, HIAL would appreciate a high level cash-flow forecast which aligns with your programme dates. This will not be assessed, rather, it will be used to help HIAL finance allocate funding across financial years for this project.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.