Construction of a 60m long, 2 span, steel and concrete composite bridge (ladder deck construction), including contractor designed piles, to replace the existing 4 span reinforced concrete structure. Construct temporary offline diversion (including temporary bridge). Demolition of existing structure.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Story Contracting Ltd | 03709861 | ~£5,000,000 estimated from lot values | 1 lot Lot 1 | DONOR£10K across 1 donation To: Cumbria Broadband Rural and Community Projects Limited |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 540 days (≈1.5 yrs) | £5,000,000 £5,501,656 initial term | 2 | Story Contracting Ltd | complete |
Weightings from the notice.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.