BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
As part of its commitment to reducing carbon emissions, the SPS has a Carbon Management Strategy in place which has identified projects that will deliver reductions to the overall carbon emissions baseline. This Carbon Management Strategy includes the installation of a 100kWp Total Installed Capacity (TIC) ground mounted Solar Photovoltaic (PV) system at HMP Dumfries. The Works involve the design, supply, installation and commissioning of the Solar PV system at HMP Dumfries, as well as cabling and associated infrastructure to integrate the PV array with the existing site electrical infrastructure. The Works also require the construction of a boundary fence.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| AES Ltd | SC084742 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £86,873 initial term | 3 | AES Ltd | complete |