BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Transport Scotland, on behalf of the Scottish Ministers, has identified the need to appoint a suitably experienced archaeological contractor (“Contractor”) to carry out non-invasive and invasive pre-construction archaeological investigations for the A9 Dualling – Tomatin to Moy Scheme.
The main objective to be delivered by the Contractor will be to reduce the effect of the A9 Dualling Programme on the archaeological resource through the acquisition of a full archaeological record and an evidence based interpretation of that record. As a minimum this will include non-invasive and invasive archaeological investigations, earthwork and landscape surveys, metal detector survey, building survey, a programme of trial trenching, followed by a post-excavation assessment and reporting, with potential strip, map and excavations, and further post excavation assessment and reporting.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| AOC Archaeology | SC506374 | ~£450,000 estimated from lot values | 1 lot Lot 1 | - |
| CFA Archaeology Ltd | SC208318 | ~£450,000 estimated from lot values | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 4 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 750 days (≈2.1 yrs) | £450,000 £632,022 initial term | 4 | AOC Archaeology CFA Archaeology Ltd | complete |
Weightings from the notice.
Government spending data: These suppliers have received £139,715 in 3 payments (over £25k) from DEFRA (2025-01-06 to 2025-02-25).
Published by the buyer on this notice. Check the original notice — details change and are not updated here.