2021 Vessel refit services of MV Varagen with repairs to commence on Monday 22 February 2021 and completion of the work contained within the specification by Sunday 7 March 2021.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Bill Mackie Engineering Ltd | SC167128 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 1 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £68,430 initial term | 1 single bid — no competition | Bill Mackie Engineering Ltd | complete |