This project provides for the replacement of the existing 250kW air cooled chiller supplying chilled water to air handling unit cooling coils serving the administration building at HMP Grampian.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| FlaktGroup UK Ltd | - | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 90 days | £85,230 initial term | 2 | FlaktGroup UK Ltd | complete |