As part of current works at the Gatty Marine Laboratory, the existing seal pool is to be refurbished to both repair defects within the concrete pool shell and surrounding slab and improve the facilities to aid with its use and maintenance by the Sea Mammal Research Unit (SMRU).
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Waterproofing Limited | SC111350 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 120 days | £420,366 initial term | 3 | Waterproofing Limited | complete |