In February 2019 the Bio Molecular Sciences (BMS) Building suffered a fire which spread into a number of laboratory areas. The efforts to extinguish the fire resulted in significant water damage to all areas and systems within the building.
The reinstatement project will be delivered in 2 phases. Phase 1 comprises the Curtain Walling and Roof repairs necessary to provide a dry “shell” ready for fitting out. Phase 2 comprises the “fit out” works. Phase 1 is under way and does not form part of this contract.
The brief is clear; the reinstated BMS building needs to provide a recognisable Biology “front door”, providing World Leading research, teaching and breakout facilities in a warm and welcoming building. Importantly the building entrance needs to reflect this. The strategy for the reinstated BMS building is summarised below:
Level 1 – Biology research, slightly reconfigured
Level 2 – Biology research, slightly reconfigured
Level 3 – Biology teaching, largely reconfigured to accommodate new function.
Level 4 – Chemistry / Biology research, slightly reconfigured
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Taylor and Fraser | - | ~£12,000,000 estimated from lot values | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 5 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 420 days (≈1.2 yrs) | £12,000,000 £11,692,366 initial term | 5 | Taylor and Fraser | complete |
Weightings from the notice.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.