2020 Vessel refit services of MV Hoy Head with repairs to commence on Monday 16 March 2020 and completion of the work contained within the specification by Friday 27 March 2020.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Bill Mackie Engineering Ltd | SC167128 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 1 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £68,481 initial term | 1 single bid — no competition | Bill Mackie Engineering Ltd | complete |