Loading contract…
BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The works comprise the removal of the existing gas fired boilers and replacement with new gas fired boilers and all associated works as per M and E designs, removal of any asbestos containing materials as highlighted in the Asbestos report. The works also include the provision of a temporary Boiler for the duration of the works.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Sparks Mechanical Services Ltd | SC102458 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 5 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £66,309 initial term | 5 | Sparks Mechanical Services Ltd | complete |