CPI require a Principal Contractor to deliver the Design and Build of the Medicines Manufacturing Innovation Centre as described within the Specification document of this ITT, by the drawings included within the Appendices.
The centre will ensure the UK is a technology and innovation leader in small molecule pharmaceutical manufacturing and will be located within the Advanced Manufacturing Innovation District Scotland (AMIDS) adjacent to Glasgow Airport. In summary, it will comprise a two storey, steel frame building on piled foundations, providing on the ground floor GMP compliant facilities including pharmaceutical cleanrooms (ISO 8) with associated materials and people air locks plus GMP compliant supporting activities.It should be noted that the layout within the technical area on the ground floor remains subject to some change within the current footprint; however the principle of there being ISO8 cleanrooms with supporting functions will remain unchanged.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Interserve Construction | - | ~£30,000,000 estimated from lot values | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 8 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 720 days (≈2 yrs) | £15,000,000 £24,000,000 initial term | 8 | Interserve Construction Interserve Construction Ltd | complete |
Weightings from the notice.