A85/04 Old Perth Bridge Bollard and Footway Works
Excavation, cutting and removal of hard material, installation of concrete strip foundation behind kerb, installation of post drilled bollards to line and level, slurry seal footway. With night time weekday single lane closure working. Refer to Scope for all requirements.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Diack & Macaulay Ltd | - | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 1 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £74,966 initial term | 1 single bid — no competition | Diack & Macaulay Ltd | complete |