BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
This requirement is for school and public bus services in Lewis and Harris, na h-Eileanan an Iar (the Outer Hebrides), Scotland, United Kingdom for a seven year period.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| alasdair macdonald | - | - | 1 lot WS3 Tolastachaolais and Callanish Feeder Service | - |
| Bus na Comhairle | - | - | 2 lots TL1 Tolsta to Stornoway Main Service · P1 Flesherin to Stornoway Main Service | - |
| Galson Motors limited | - | - | 1 lot WS4 Shawbost & Westside School & Carloway to Stornoway | - |
| I.A. & C. MACIVER LIMITED | SC146898 | - | 3 lots SY1 Melbost to the Nicolson Institute and Stornoway Primary · SY2 Newmarket and Newvalley to the Nicolson Institute · WS1 Westside Circular Main Service | - |
| LOCHS MOTOR TRANSPORT LTD | SC025065 | ~£9,730,000 estimated from lot values | 4 lots L1 Ness - Stornoway · L4 North Lochs, South Lochs & Harris North Spine · H1 Harris · P2 Point to the Nicolson Institute & Sgoil na Rubha | - |
| MacLennan Coaches | - | - | 1 lot TL2 Tolsta to Stornoway School Service | - |
| M. MACIVER (MINIBUSES) LTD | SC296127 | - | 2 lots WS2 Carloway District Feeder · BR1 Bernera District to Garynahine | - |
| PETER MACLENNAN | - | - | 1 lot UG1 Uig District to Garynahine and Stornoway | - |
This procurement was divided into 54 lots, each awarded separately. 27 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 12 UG1 Uig District to Garynahine and Stornoway 2,520 days (≈6.9 yrs) | £1,096,900 initial term | 2 | PETER MACLENNAN | complete |
| Lot 13 UB1 Brenish to the Nicolson Institute 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 14 BR1 Bernera District to Garynahine 2,520 days (≈6.9 yrs) | £689,801 initial term | 1 single bid — no competition | M. MACIVER (MINIBUSES) LTD | complete |
| Lot 15 UG2E Uig District to Stornoway Saturday Evenings 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 17 TL1 Tolsta to Stornoway Main Service 2,520 days (≈6.9 yrs) | £1,463,000 initial term | 2 | Bus na Comhairle | complete |
| Lot 18 TL2 Tolsta to Stornoway School Service 2,520 days (≈6.9 yrs) | £1,216,950 initial term | 3 | MacLennan Coaches | complete |
| Lot 19 TL6E Stornoway to Tolsta Evenings 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 20 P1 Flesherin to Stornoway Main Service 2,520 days (≈6.9 yrs) | £1,785,000 initial term | 3 | Bus na Comhairle | complete |
| Lot 21 P2 Point to the Nicolson Institute & Sgoil na Rubha 2,520 days (≈6.9 yrs) | £1,058,750 initial term | 4 | LOCHS MOTOR TRANSPORT LTD | complete |
| Lot 22 P6E Stornoway to Flesherin Evenings 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 25 SY4B Creed and Newvalley to Laxdale School 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 26 SY4C Newmarket and Manor to Laxdale School 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 27 NL1 Ranish to Stornoway and Grimshader Feeder Service 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 28 NL3 Ranish to Sgoil nan Loch 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 29 NL4 Keose Feeder and Achmore to Sgoil nan Loch 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 30 NL5 Arivruach to Sgoil nan Loch 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 31 SL1 South Lochs District to Balallan & Stornoway 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 32 SL2 Gravir to the Nicolson Institute 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 33 SL3a Stornoway Aline & Rhenigidale to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 34 SL3b South Lochs to Stornoway & Aline to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 35 SL3c South Lochs District to Stornoway 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 36 HA1 South Harris to Stornoway & Scalpay to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 37 HA2 Borrisdale Feeder to Leverburgh and Northton 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 38 HA9 East Harris Bays to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 39 HA10 Rodel to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 40 HAR1 South Harris to Tarbert & Stornoway 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 41 HAR2 South and East Harris to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 42 HAR3 Scalpay to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 44 HAR5 Aline & Rhenigidale to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
| Lot 45 HAR6 East Harris, Golden Road to Tarbert 2,520 days (≈6.9 yrs) | - | - | - | unsuccessful |
Government spending data: These suppliers have received £3,395 in 3 payments (over £25k) from Department for Transport, DLUHC (2012-10-29 to 2024-02-09).
Changes the buyer published to this notice after it first appeared.
To allow 15 days from the date of publication in accordance with the Public Contracts (Scotland) Regulations 2015 on the basis of urgency.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.