Loading contract…
BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Asbestos surveying and management
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| sgs mis environmental limited | 04183187 | - | 5 lots Carry our Full Demolition / Refurbishment Survey to individual empty properties (Internal and External) up to 10 samples to be completed within 3 working days. · – Carry out Full Demolition / Refurbishment Survey to Communal Areas of Blocks of Flats up to 10 samples (Internal and External) to be completed within 10 working days. · Carry out Part Refurbishment/ Part Management Survey to individual property (Internal and External) to include taking up to 4 samples as part of the survey. To be completed within 10 working days. · D - Carry our Full Demolition / Refurbishment Survey to individual property or block (External only) · Manage the process of any removals with the appointed contractor | - |
This procurement was divided into 5 lots, each awarded separately. 50 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Carry out Part Refurbishment/ Part Management Survey to individual property (Internal and External) to include taking up to 4 samples as part of the survey. To be completed within 10 working days. 720 days (≈2 yrs) | - | 10 | sgs mis environmental limited | complete |
| Lot 2 Carry our Full Demolition / Refurbishment Survey to individual empty properties (Internal and External) up to 10 samples to be completed within 3 working days. 720 days (≈2 yrs) | - | 10 | sgs mis environmental limited | complete |
| Lot 3 – Carry out Full Demolition / Refurbishment Survey to Communal Areas of Blocks of Flats up to 10 samples (Internal and External) to be completed within 10 working days. 720 days (≈2 yrs) | - | 10 | sgs mis environmental limited | complete |
| Lot 4 D - Carry our Full Demolition / Refurbishment Survey to individual property or block (External only) 720 days (≈2 yrs) | - | 10 | sgs mis environmental limited | complete |
| Lot 5 Manage the process of any removals with the appointed contractor 720 days (≈2 yrs) | - | 10 | sgs mis environmental limited | complete |
Weightings from the notice, applied to every lot.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.