Quay wall repair to an area of slippage in the outer basin of Arbroath Harbour. Including, but not limited to, concrete works, scour repair, stone work and site clearance etc.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| delson contracts ltd | SC133992 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 8 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £193,492 initial term | 8 | delson contracts ltd | complete |