In order to achieve our harvesting programme, income targets, and to supply Forestry and Land Scotland customers via Long Term Contracts and sales events held throughout the year, Forestry and Land Scotland require to have in place Medium Term Contracts (MTCs) for the provision of harvesting and extraction to roadside for the Forest Regions.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| AMAC harvesting | SC453984 | ~£2,876,050 estimated from lot values | 1 lot North Region - Clearfell | - |
| Blacklock harvesting Ltd | 06799426 | ~£1,300,000 estimated from lot values | 1 lot East Region - Durris | - |
| David S Prosser | - | ~£1,000,000 estimated from lot values | 1 lot East Region - Various Sites | - |
| Dick Brothers Ltd | SC153358 | ~£4,565,000 estimated from lot values | 4 lots Central Region · Winch Work - West Region · East Region - Huntly · West Region | - |
| Elliot Henderson Ltd | SC207550 | ~£1,840,000 estimated from lot values | 1 lot South Region (West) | - |
| Greenlees Harvesting Ltd | - | ~£1,650,000 estimated from lot values | 1 lot East Region - Moray | - |
| Speyside Harvesting Ltd | SC246008 | ~£878,000 estimated from lot values | 1 lot North Region Thinning | - |
This procurement was divided into 10 lots, each awarded separately. 33 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 South Region (West) 1,440 days (≈3.9 yrs) | £1,840,000 £1,083,944 initial term | 5 | Elliot Henderson Ltd | complete |
| Lot 2 North Region - Clearfell 1,440 days (≈3.9 yrs) | £2,876,050 £2,972,864 initial term | 4 | AMAC harvesting | complete |
| Lot 3 North Region Thinning 1,440 days (≈3.9 yrs) | £878,000 £891,000 initial term | 1 single bid — no competition | Speyside Harvesting Ltd | complete |
| Lot 4 Central Region 1,440 days (≈3.9 yrs) | £465,000 £383,772 initial term | 3 | Dick Brothers Ltd | complete |
| Lot 5 Winch Work - West Region 1,440 days (≈3.9 yrs) | £1,120,000 £921,976 initial term | 2 | Dick Brothers Ltd | complete |
| Lot 6 West Region 1,440 days (≈3.9 yrs) | £1,680,000 £1,267,407 initial term | 4 | Dick Brothers Ltd | complete |
| Lot 7 East Region - Moray 1,440 days (≈3.9 yrs) | £1,650,000 £1,267,310 initial term | 2 | Greenlees Harvesting Ltd | complete |
| Lot 10 East Region - Various Sites 1,440 days (≈3.9 yrs) | £1,000,000 £291,192 initial term | 2 | David S Prosser | complete |
| Lot 8 East Region - Durris 1,440 days (≈3.9 yrs) | £1,300,000 £1,066,780 initial term | 4 | Blacklock harvesting Ltd | complete |
| Lot 9 East Region - Huntly 1,440 days (≈3.9 yrs) | £1,300,000 £718,502 initial term | 6 | Dick Brothers Ltd | complete |
Weightings from the notice, applied to every lot.
Government spending data: These suppliers have received £868,197 in 33 payments (over £25k) from Forestry Commission (2018-03-20 to 2025-05-01).
Published by the buyer on this notice. Check the original notice — details change and are not updated here.