Scottish water requires contractor(s) to operate, service and maintain our hydro power assets to maximise generation and performance. The contractor will be required to attend sites across mainland Scotland. The schemes are split in to two lots, one being slightly north of the central belt and the other within or south of the central belt.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Gilbert Gilkes & Gordon Ltd | 00173768 | - | 2 lots Hydro Southern · Hydro Northern | - |
| Ross-shire Engineering Ltd | SC177939 | - | 2 lots Hydro Southern · Hydro Northern | - |
This procurement was divided into 2 lots, each awarded separately. 4 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Hydro Northern Feb 2020 – Mar 2024 | - | - | Gilbert Gilkes & Gordon Ltd Ross-shire Engineering Ltd | complete |
| Lot 2 Hydro Southern Feb 2020 – Mar 2024 | - | 4 | Gilbert Gilkes & Gordon Ltd Ross-shire Engineering Ltd | complete |