The existing main steam line in the Llansamlet Laundry was installed in the 1980s, it is in poor condition and corroded due to this the boilers in the laundry cannot be utilised at full capacity. The steam line currently runs under 7Bar meaning there is a loss of efficiency on plant machinery.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 90 days | - | active |