The construction works is currently limited to the Phase 2 and 3 Infrastructure Works comprising of approximately 1.3 km of single carriageway highway including priority junctions and roundabouts, footways and cycleway links, associated earthworks, drainage, culverts, street furniture, lighting, services, accommodation works, service diversions and environmental mitigation works.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| D Morgan PLC | 00797565 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 | £7,740,401 initial term | 2 | D Morgan PLC | complete |
Weightings from the notice.
Government spending data: This supplier has received £10,283,374 in 23 payments (over £25k) from Welsh Government (2022-09-22 to 2025-08-21). View full payment history →