BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Yarborough Road
The project consists of the removal of the existing retaining walls and layby at the top of Whittons Park. This will then be replaced by a reinforced earth (plastic grids, imported fill) slope that ties into the park. The works will consist of the following disciplines, earthworks, drainage, surfacing, kerbing, footways, street lighting, lining, fencing and landscaping. The project has an agreed satellite compound at the base of the park to handle materials.
Ropewalk Gyratory
The project consists of the reconstruction/resurfacing of Ropewalk Gyratory outside Lincoln University from Brayford Wharf East to Centaur Road (Morrisons) to Brayford Way (McDonalds). As part of these works the signals will be refreshed by LCC with the civils elements such as new socket installation being undertaken as part of this contract. There will also be new kerb and footway works included in the package. The works will consist of the following disciplines, drainage, surfacing, kerbing, footways, street lighting and lining. It is expected that the main compound will be positioned on Beevor Street for both sites due to exiting hard standing being in place
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| BREHENY CIVIL ENGINEERING LIMITED | 00753976 | £4,254,862 | 1 lot Lot 1 | - |
Taken from this notice, not from Companies House. Check the original notice — details change and are not updated here.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | - | active |
Government spending data: This supplier has received £43,632,562 in 540 payments (over £25k) from DEFRA, Department for Transport (2012-06-26 to 2026-02-19). View full payment history →