BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
This project primarily comprises of the replacement of the automatic change over panel linking the backup generator to the main electrical intake. This is to be completed at 5No. Adult Healthcare sites. Contractor is to undertake a full electrical shutdown of each site, while supporting all critical life safety systems during this period. Note, all sites are operational 24/7. Works to be completed within 6-weeks.
Works are to be completed at the below healthcare sites:
The works can be summarised as follows:
Main contractor will require on site support from incumbent term maintenance contractor Corrigenda, lift specialist, fire alarm & security alarm specialist at each site when isolating and reenergising the mains electrical supply ensuring all systems come back online and are fully operational.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| CEI ELECTRICAL SERVICES LTD | 14182998 | £65,775 | 1 lot Lot 1 | - |
Taken from this notice, not from Companies House. Check the original notice — details change and are not updated here.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | £65,775 initial term | active |