BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Overview
Littlehampton Town Council is seeking to appoint a suitably qualified and experienced Contractor to provide a comprehensive internal design and fit-out service in respect of the proposed Hub on the High Street ("The Hub")
The appointed Contractor will be responsible for delivering the project from an empty shell condition through to a fully completed, compliant, and operational space ready for occupation and use. The Council's intention is to appoint a single Contractor capable of providing an integrated design and build solution, including all necessary design, specification, supply, installation, coordination, and commissioning activities.
Scope of Services
The Services shall include, but shall not be limited to, the following elements:
Internal Design Services
The Contractor shall:
Fit-Out and Construction Services
The Contractor shall undertake all works necessary to transform the shell space into a completed and operational Hub. This shall include:
Accessibility, Compliance and Standards
The completed Hub must:
Handover and Completion
Upon completion, the Contractor shall provide:
Programme and Budget
Tenderers will be required to propose a realistic programme for design, mobilisation, and completion of works. The Council requires timely delivery and minimal disruption to the surrounding High Street environment.
The Contractor must demonstrate cost control mechanisms and deliver the project within the agreed contract sum.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 May 2026 – Sept 2026 | £100,000 | active |
Weightings from the notice.
Changes the buyer published to this notice after it first appeared.
Added supporting documents to aid tender bids. Includes PDF/CAD drawing of the building, and a question and answer document addressing questions received around the tender.
Revised site visit dates confirmed and added, tender deadline for submissions timeline extended in line with this