This project is to rewire Brierley Hill fire station, this includes removal of all existing cables/switchgear/distribution boards/lighting and replace for new as per the specification.
A decision is to be made if the station is closed or not for the duration of the works, within the tender documents there are two options that will be required to be completed and costed for.
Option 1: Works To Be Carried Out Over One Phase, Whilst Building is Vacated
Option 2: Works To Be Carried Out in A Phased Manner, Whilst Building is Occupied/Operational
The decision will be made by senior leaders within the organisation using the information provided within this tender response, including costs, timeframes, disruption to site, Health and safety of contractors and WMFS personnel.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Jun 2026 – Dec 2026 | £180,000 | active |