Project Overview
1.1 The route to market being considered is the Competitive Flexible Procedure. This will comprise of a Request to Participate stage with Conditions of Participation questions and an Invitation to Tender stage.
1.2 The scope of the project is to redevelop two existing sites, to accommodate the British High Commission. The British High Commission (Ghana) estate is made up of two sites that sit side by side. It is located on Julius Nyerere Link Road in a reasonably affluent and central part of Accra, close to Parliament, the Presidency and some Ministries. The office estate in Accra is tired and in poor condition (in places), having suffered from a lack of strategic investment and maintenance.
1.3 It is anticipated that the consturction will take place in phases. Work will start at the Volta site which will be vacant throughout construction (staff normally based at this site will be temporarily moved to the Afadja Site). Once construction works at the Volta site are complete, all of the staff at the Afadja site will be transferred to the Volta site to enable the phase 2 works to be undertaken in the unoccupied Afadja building.
1.4 In line with the overall estate strategy, the intention is to have the Volta HC Office staff move to the Afadja High Commission for the duration of the Volta construction period.
1.5 The existing sites comprises of:
1.6 Part of the site development design includes:
1.7 The Contractor, as well as any engaged sub-contractors, are required to perform all work in accordance with the relevant UK Standards. The construction must meet established UK standards throughout the build process.
2. It is anticipated that the works will be undertaken under the NEC form of contract; ECC 4, Option A (Priced Contract with an Activity Schedule).
3. The project team is also considering the inclusion of an Early Contractor Involvement stage ahead of the construction stage. Both stages will be within the same contract.
4. Some areas of the building will be classified as higher security and will require a separate specialist contractor. These works will not form part of this requirement/contract. However, the parameter and interface between the higher classified areas and the works within this requirement will require security cleared personnel at Security Check (SC*) level to manage the works. Contractor’s will need to be able to provide such personnel before the works contract can begin.
*SC is a process of security vetting. Further details can be found at https://www.gov.uk/government/publications/united-kingdom-security-vetting-clearance-levels/national-security-vetting-clearance-levels#security-check-sc.
5. Below is a schedule of key market engagement and tendering activities (subject to change):
Activity Date
Submit PME questionnaire Response 23rd February 2026
1:1 Discussions with Bidders W/C 2nd March 2026
Issue ITT Summer/Autumn 2026
Bidders day Summer/Autumn 2026
Proposed Bid Deadline Autumn/Winter 2026
Contract Award Winter 2026
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Dec 2026 – Aug 2029 | - | planning |