The main tasks include: 1. Installation of a new sewage treatment plant and related infrastructure; 2. Pipelaying with manholes through the highway to gravity-dispose the treated effluent to a surface water course approximately 200m away; 3. Connection of the foul drains from these four houses to the plant; 4. Removal of the current cesspools by filling them with excavated materials and making good to match existing.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| COLLINSSONS LIMITED | 10213858 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | - | active |