The primary objective of the Mill Lane bridge works is to ensure the structural integrity of the two bridge structures for approximately 50 years, and the removal of the temporary 3t weight limit restrictions without excessive costs in compliance.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| HYDROLINE SOLUTIONS LIMITED | 07600223 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | £74,846 initial term | active |