BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The King Charles III England Coast Path (ECP) is a nationwide initiative to provide a 2,700-mile National Trail and is being funded through Natural England's approved scheme.
All funded stretches of the Coast Path must remain in use, and funded items remain functional and fit for purpose, for 5 years from the date of final payment of grant.
To deliver a trail around the Island the Isle of Wight Council has identified ten stretches and six of these have been approved by DEFRA with the funding in place.
Section IOW3 is one of those approved and funded and requiring completion at the earliest opportunity.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Crown Park Builders Ltd | 03177821 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | £102,728 initial term | Crown Park Builders Ltd | active |