AWARDEDProcurement termination notice (UK12) · THE PIRBRIGHT INSTITUTERef ocds-h6vhtk-05cead
Site Steam Upgrade Project - Principal Contractor & Installation Package
Save Track Track buyer
Contract Value
£320,000
excluding VAT · £384,000 including VAT · Below the relevant threshold
The purpose of this project is to increase the Institute’s sustainability (both environmental & financial), reduce carbon emissions and safeguard the steam supply to all buildings utilising steam generated at Pirbright.
This will be achieved by a combination of the following three factors:
New steam main & condensate recovery system to steam users currently served by the end of life Western Boiler House.
Removal of inefficient and end of life Western Boiler house & increasing load on the currently underutilised, efficient, EC1 steam generation plant by 450kWh (585 kg/hr).
Upgrading 2 of 4 EC1 steam boilers with burners capable of 10:1 turndown ratio to enable more efficient operation at low production rates during summer months.
Contract Scope
The contract is for a single supplier to act as the Principal Contractor and complete all works as follows:
Supporting the Stage 4 design with client nominated designer and Project Manager
Supply and Installation of EC1 steam boiler burners (x2).