Additional lead works to turret, including the necessary timber repair
Remove flaking paint from leadwork to the top two levels of the
28-square-metre turret
Triflex Pro Tect is installed on the remaining lead work to the top two levels (35m²)
Install Triflex Pro Tect on the two remaining lead flat roofs
Ensure that stone repairs are carried out and that the crest is painted on the front of the building
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| JAMES ROOFING & CONSTRUCTION LTD | 09584192 | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | £32,700 initial term | active |