1.The objective of this Contract is to deliver a suite of Moorland Restoration Works on 2 areas in the Upper Derwent Valley in the Peak District National Park. The sites are split into 6 packages of Works. The aim of the Works suites are to stabilise and revegetate bare peat, restore hydrology, and increase biodiversity on the Sites.
2. The Works contain multiple years with work periods between August 2025 and 31st March 2028.
3. The Works comprise the following tasks:
a. Supply and delivery of Materials required to complete the Works, unless otherwise stated.
b. Appropriate storage of Materials, as necessary.
c. Supply and delivery of suitable Trackway for storing materials on (see Packages if required).
d. Forwarding of Materials and Equipment required to complete the Works to and within Works Sites, excluding Airlifting e. Planning the Aerial Load Lifting Works, including marking out drop locations and working in collaboration with the Authorities Airlifting Contractor to deliver the works f. Marshalling of Aerial Load Lifting, including materials drops g. Installation of Stone Dams into gullies h. Installation of Peat Dams into gullies i. Re-profiling of hags and gully sides j. Installation of Timber Dams into gullies k. Installation of Heather Bales/coir logs into gullies and peat pans l. Spreading of Heather Brash on bare peat m. Supply of lime and fertiliser (NOT seed) n. Spreading of Lime, Seed, and Fertiliser o. Planting of sphagnum plug plants p. Planting of vascular plug plants q. Cutting and bagging of heather brash and bales r. Removal of Waste Materials from Sites.
4. Total Works
Brash - 2333
Lime seed and fertiliser - 27.53
Supply of Heather Brash - 1408
Supply of Heather Bales - 150
Gully Blocking - Coir Logs - 396
Gully Blocking Peat Dams - 390
Gully Blocking Stone dams - 1338
Gully blocking - Timber dams - 750
Reprofiling - 2700
Sphagnum planting - 610000
Vascular Plug planting - 103500
Sphagnum Pool mix planting - 16680
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| CONSERVEFOR LIMITED | 07925958 | £226,813 | 1 lot Package 2 -Westend Head Swains Greave Ground Works | - |
| ENVIRONMENTAL LAND MANAGEMENT SOLUTIONS LIMITED | 10379504 | £271,840 | 1 lot Package 1 - Raven's Clough (Birchinlee) | - |
| Michael Wynne | Procurement ID: PRTT-3667-VBJX | £47,254 | 1 lot Package 3a Heather Brash supply | - |
| RIVER STEWARDSHIP COMPANY LIMITED | 06759419 | £43,390 | 1 lot Package 5 - Raven's Clough Planting Works | - |
| UPLAND ENVIRONMENTAL LTD | 15807029 | £112,595 | 1 lot Package 4 - Westend Head Swains Greave Planting Works | - |
Taken from this notice, not from Companies House. Check the original notice — details change and are not updated here.
This procurement was divided into 6 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 Package 1 - Raven's Clough (Birchinlee) Sept 2025 – Mar 2026 | £381,000 £271,840 initial term | active | |
| Lot 2 Package 2 -Westend Head Swains Greave Ground Works Aug 2025 – Mar 2028 | £225,000 £226,813 initial term | active | |
| Lot 3 Package 3a Heather Brash supply Aug 2025 – Dec 2025 | £56,320 £47,254 initial term | Michael Wynne | active |
| Lot 4 Package 4 - Westend Head Swains Greave Planting Works Aug 2025 – Mar 2027 | £110,000 £112,595 initial term | active | |
| Lot 5 Package 5 - Raven's Clough Planting Works Aug 2025 – Mar 2027 | £43,390 | active | |
| Lot 6 Package 3b Heather Bale supply Aug 2025 – Dec 2025 | £6,000 | - | active |
Weightings from the notice, applied to every lot.