The works under this contract comprise the co-ordination, management, administration, and completion of works for Planned Preventative Maintenance (PPM), Responsive Repairs, Planned Repairs and Call Outs for Pool Plant, Sauna, Steam Rooms and ancillary equipment to ensure that all under this agreement meet health & safety requirements and are maintained appropriately, for sites within the County of North Yorkshire and surrounding Council Authority areas including (but not limited to) the following types of works as specified in the Technical Specification: - Pool Plant, Filtration System, Saunas, Steam Rooms, Pool Covers, Pool Moving Floors, UV Systems, Chemical Dosing, Pool Tank Inspections
The form of contract is JCT Measured Term Contract 2024, the Employer gives no warranty or undertaking as to the actual amount of work that will be ordered through this contract.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| STERLING HYDROTECH LIMITED | 02275897 | £541,667 | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 4 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Sept 2025 – Sept 2027 | £687,087 £541,667 initial term | 4 | active |
Weightings from the notice.
Government spending data: This supplier has received £2,388 in 3 payments (over £25k) from Guy's and St Thomas' NHS FT (2023-08-04 to 2024-05-03). View full payment history →