The planned works shall consist of external wall insulation renewal, lower flat roof renewal, Atrium skylight renewal and BMS alternations, renewal of window actuators and controllers with associated works.
o commence the works on 10 July 2025 concluding 01 October 2025.
The scaffolding is to be erected ahead of commencement and execution of the formal contract under the terms of letter of intent.
Completed as part of the redevelopment programme in 2008, the Rolle Building provides academic space and purpose-built office space for administration staff.
On the eastern and western facades a perforated metal sheet in the form of a curved solar shading system supported by metal framework. The design intent of the brise soleil drew inspiration from the undulated brise soleil of the Babbage Building, which has since been overhauled.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Jul 2025 – Oct 2025 | £1,500,000 | planned |