Orkney Islands Council (OIC) is developing Orkney Community Wind Farms, comprising two windfarms in the Orkney Islands. Quanterness wind farm, located on Mainland Orkney (Northwest of Kirkwall), consisting of six circa 4.8 MW Wind Turbine Generators. Faray wind farm, located on the uninhabited island of Faray in the North isles, consisting of six circa 4.8 MW Wind Turbine Generators. Both wind farms have obtained all planning consent and grid connection agreements. Quanterness is due to commence operation in June 2028, with Faray commencing operation in May 2030.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Heddle Construction Ltd | - | £14,053,315 | 1 lot Quanterness Wind Farm - ECC | - |
Taken from this notice, not from Companies House. Check the original notice — details change and are not updated here.
This procurement was divided into 2 lots, each awarded separately. 2 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Quanterness Wind Farm - ECC 720 days (≈2 yrs) | £7,000,000 £14,053,315 initial term | 2 | Heddle Construction Ltd | active |
| Lot 2 Faray Wind Farm - ECI 1,080 days (≈3 yrs) | £11,000,000 | - | - | active |
Weightings from the notice, applied to every lot.