The Royal Institution resides in a Grade I listed building located on Albemarle Street, Mayfair within the City of Westminster.
Project Description
The Royal Institution's mission for over two centuries has been to connect people with science on a global scale.
As an independent registered charity, the Ri is committed to science education, public engagement, and heritage activities, catering to diverse audiences worldwide.
Entering a new strategic phase, the Ri envisions science accessible to all, believing in its transformative power across various aspects of modern life. As advocates for equitable access to science, the Ri bridges the gap between the public and scientists, nurturing curiosity, exploration, and engagement. It serves as a welcoming home for science enthusiasts of all backgrounds.
To support this goal Ri has secured £4.35 million in funding from the Greater London Authority (GLA) for its Footprint Project to reduce the environmental impact of the building. This funding will be the catalyst for a comprehensive retrofit of the building, including the improvement of building plant, services and systems and sensitive enhancement of building fabric. The Footprint Project should serve as a precedent for successfully retrofitting a Grade I listed building to mitigate environmental impact and provide climate resilience.
Ri project objectives
Project scope
Proposals have been developed through:
In optimising the project scope and ambition with the heritage and immediate GLA funding and key programme drivers, the design team has made recommendations on how the works could be phased.
The works are planned to commence as soon as possible after 2nd June 2025 award date and a Listed Building Consent Application has been submitted on 28th February 2025 to enable those works. The Royal Institution will require excessively noisy works and those that will affect the use most of the internal areas to be carried out during a 6 weeks operationally reduced activity period for the Ri commencing on 25th July 25 and ending on 5th September 25. At present the works to be executed during this operationally reduced activity period are as follows :-
Builders work (including roof penetrations for ducting) and access hatch
Metalwork replacement
Balustrades
ASHP installation only
AHU installation only
Steelworks and roof penetration for Louvres
Waterproofing/making good of roof
Radiators, air curtains replacement including connecting and adapting to existing pipework and cabling
Making good works related to new radiators and air curtains to a like for like condition
Window films
LED Lighting to front of house rooms
BMS works
Glazed doors and screens
Fire stopping and decommissioning gas connection in kitchen
Renewing some kitchen equipment (replacing gas appliances with electric)
The remaining works that can be completed during the period after the 5th September up to 28th November 25 are currently considered to be as follows :-
VrF installation to No. 20
Roof internal insulation
ASHP (on roof) connecting to power and commissioning
AHU (on roof) connecting to power and commissioning
Louvres installation
BMS commissioning
Directors' Flat works
LED lighting to back of house rooms and external areas
Tenders will be sought on a fixed price basis. The form of contract will be JCT Standard Form of Building Contract without quantities 2024 with amendments. The contract will also contain some Contractor Design Portions.
The timeline for selecting a contractor shall be as follows :-
Issue Notice with SQ - 5th March 25
Date for returning SQ - 13th March 25
Reviewing SQs and selection of tenderers - 20th March 25
Issuing ITT to selecting tenderers - 21st March 25
Tender return date (ITT) - 21st April 25
Target contract Award - 2nd June 25
This notice invites contractors to complete and submit the selection questionnaire attached to this notice. This should be returned to D R Nolans & Co ltd via email by 5pm (GMT) on Thursday 13th March 25 as noted above. The SQ includes questions relating to the tenderers business, financial standing, ability to act as Principal Contractor under the Building Safety Act, compliance as well as quality questions. The scoring is indicated on the SQ form.
Copies of work in progress Stage 4 drawings prepared by the Architect (BDP), MEP Engineer (Harley Haddow) and Structural Engineer (Price & Myers) attached for information regarding the scope of works. Other principal consultants involved in the projects are Project Managers (Gardiner & Theobald) and Cost Consultant (D R Nolans & Co).
The SQs received will be reviewed and scored and a maximum of five contractors will be invited to submit full tenders for the works in accordance with the timings noted above.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Jun 2025 – Nov 2025 | - | active |