Loading contract…
BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Works and modification to be undertaken on current heating system at Warrington Hospital.
Total cost of £ 71,584.84 + vat The project would take approx. 3 months to complete
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| JK Engineering Limited | - | - | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Awarded To | Status |
|---|---|---|---|
| Lot 1 | £71,585 initial term | JK Engineering Limited | active |