Construction contract to fit out a ground floor area of the existing hospital to provide a new aseptic suite as well as constructing a new steel framed plant room on the roof (which is directly above the ground floor/single storey area where the aseptic suite will be located) to accommodate the plant for the same.
Given the specialist nature of the fit out there will be a requirement to sub-contract the clean room fit out (other than MEP) to a clean room specialist.
The proposed contract is the JCT Standard Building Contract without quantities with a small number of CDP packages. Procurement will be via a single stage process.
The process is being managed by Gardiner & Theobald LLP on behalf of The Royal Marsden. Please contact Kat Clover on …@gardiner.com for further details if you are interested in this opportunity and believe you are competent to deliver the same.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 270 days | £5,000,000 | active |