Thames Water has planned for 570km to be delivered during AMP8 (with a further 1,000km in AMP9). The intention is to split this between water quality driven mains rehab (12km), burst driven mains rehab (108km) and whole DMA replacement (380km). This framework is intended to compliment the existing framework by providing supplementary support in addressing the evolving demands of the current framework in the next AMP and going forward.
The aim of the AMP8 Distribution Mains Renewal Programme is to replace the pipework (excluding new polyethylene) within the worst performing DMAs so that the amount of leakage in each of those areas is reduced.
The business drivers for the schemes are:
The objective of the Distribution Mains Renewal Programme is the structural renewal of targeted water distribution mains and all associated apparatus in the network to reduce bursts and leakage.
Renewal of the water mains network shall include but not be limited to:
No supplier information available.
This procurement was divided into 2 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 Design and Build | - | planned |
| Lot 2 Build Only | - | planned |