BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Construction of Phase 1 of Block A apartments at Graven Hill, this is a single block building over 4 stories, with two stair cores and 1 lift, containing a mixture of 1 & 2 bed apartments, totaling 44 in number, with the ground floor including 2 of these apartments, then the remaining space being subdivided into 3 commercial units, which will be delivered to shell only. All external landscaping including car park, car charging points, cycle storage & the civils work required to install a new substation are included in the package of works.
No supplier information available.
This procurement was divided into 1 lots, each awarded separately.
| Lot | Value | Status |
|---|---|---|
| Lot 1 360 days | £9,600,000 | active |