The site was acquired by Stonewater Developments Limited (the development arm of Stonewater Limited) in March 2021 with the aim of constructing the new homes using modular form of construction and the apartments in a traditional form of construction. The site was initially contracted to a different provider, to be delivered as a modular build. The site clearance works, substructure and installation of the 114no modular houses, the structures, external walls and pre-cast concrete planks to the intermediate floors and roof of the traditional constructed apartment block and the site infrastructure works have progressed.
Works were initially delayed due to design and buildability issues with the proposed modular flat roofs. This resulted in a planning non-material amendment being obtained revising the design to traditional pitch roofs. These works have commenced. However, the main contractor entered into Administration on 12th June 2023 and the build contract has been terminated.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Edenstone | - | ~£5,500,000 estimated from lot values | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 4 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 720 days (≈2 yrs) | £5,500,000 £6,396,075 initial term | 4 | Edenstone | active |
Weightings from the notice.
Published by the buyer on this notice. Check the original notice — details change and are not updated here.