BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
The requirement is for a high purity hydrogen generator capable of producing a stable and uninterrupted flow of high purity hydrogen gas to multiple MOVPE reactors in a semiconductor manufacturing facility.
The existing hydrogen generation system is sited within the facility building in a ventilated steel enclosure with a footprint of 3.6m x 4.8m, max height 2.8 m. The new system can either be installed within this existing envelope or in an external location in a suitable weatherproof enclosure to be supplied as part of the tender.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| H2B2 Electrolysis Technologies SL | - | ~£690,000 estimated from lot values | 1 lot Lot 1 | - |
This procurement was divided into 1 lots, each awarded separately. 3 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Oct 2023 – Oct 2024 | £690,000 £679,907 initial term | 3 | H2B2 Electrolysis Technologies SL | active |
Weightings from the notice.
Published by the buyer on this notice. Details change and are not updated here.