BETAThis is a new independent transparency project, not an official government website. The data is sourced from public registers and may contain errors, so always verify against the official source. If you find a problem, please report it here.
Southern Water Services (SWS) is anticipating that AMP8 will be the largest investment programme it has ever undertaken, given its plans for WINEP and WRMP, and the service it is seeking to deliver for customers. SWS now wishes to secure a range of supply chain partners for the delivery of its AMP8 capital programme. The AMP8 regulatory period will run from April 2025 to March 2030. The current frameworks used for engineering, design and construction services have been in place for almost 10 years and expire on 31st March 2025. In procuring new frameworks, we are seeking to build on positive changes made in AMP7, but also to look beyond AMP8 and take important steps to reflect supplier feedback, moving towards excellence in all that we do. The new arrangements will offer the option of running for AMP9.
In parallel to this procurement process, Southern Water is working up its plans for PR24 – including working with our regulators and stakeholders to confirm the investment that will be available, and the capital delivery projects that will need to be undertaken. The PR24 process will benefit from having the AMP8 supply chain in place to assist with ongoing planning and transition to AMP8.
A collaborative framework will be established to deliver low complexity infrastructure design and build schemes. The framework will have 2 lots one for water and wastewater.
A framework for Non-Infrastructure works has already been established for the remainder of AMP 7 and 8.
The Partner shall work with the Client to provide engineering capability and expertise to: Identify and develop options in accordance with the Client’s technical and engineering standards for all aspects of Water and Wastewater systems.
| Supplier | Identifier | Award Value | Lots Won | Cross-References |
|---|---|---|---|---|
| Barhale Limited | 01268005 | ~£294,000,000 estimated from lot values | 1 lot Capital Infrastructure Water | - |
| Clancy Docwra Limited | 00432242 | ~£294,000,000 estimated from lot values | 1 lot Capital Infrastructure Water | - |
| J Browne Construction Limited | - | ~£406,000,000 estimated from lot values | 1 lot Capital Infrastructure Wastewater | - |
| Morrisons Water Services Limited | - | ~£406,000,000 estimated from lot values | 1 lot Capital Infrastructure Wastewater | - |
| United Living Infrastructure Services | - | ~£294,000,000 estimated from lot values | 1 lot Capital Infrastructure Water | - |
This procurement was divided into 2 lots, each awarded separately. 23 bids were received in total.
| Lot | Value | Bids Received | Awarded To | Status |
|---|---|---|---|---|
| Lot 1 Capital Infrastructure Water 1,800 days (≈4.9 yrs) | £294,000,000 £236,700,000 initial term | 5 | Clancy Docwra Limited Barhale Limited United Living Infrastructure Services | active |
| Lot 2 Capital Infrastructure Wastewater 1,800 days (≈4.9 yrs) | £406,000,000 £192,000,000 initial term | 4 | J Browne Construction Limited Morrisons Water Services Limited | active |
Weightings from the notice, applied to every lot.
Published by the buyer on this notice. Details change and are not updated here.